Access road
Road width and grade for equipment and haul traffic
Proposed project · unverified items are not established facts
05 — Development & production
Infrastructure, equipment, process and throughput, joined in one execution plan.
Roadmap
Incorporation, operating rights, technology scope
Independent ore assays, recovery tests per metal
Site and process design, mining plan application, funding plan
Trial run for quality and cost, then commercial production
Mining plan approval has not yet been obtained; mining and production follow once approvals are in place.
Mine infrastructure
From the access road to power and water, the groundwork for mining and processing is designed together.
Road width and grade for equipment and haul traffic
Portal works; tunnel profile and support sized to equipment
Ore stockpile, processing plant, workshop and stores, site office
Power supply, process water, ventilation and drainage, comms
Equipment plan
One drilling, loading and haulage set per working area. Models are finalised after tunnel surveys and quotes.

Drilling
Single-boom development drill rig
Drills the face to advance tunnels and start mining.
Manufacturer spec · 24 m² coverage · 43–64 mm holes

Loading
Narrow-vein underground loader (LHD)
Loads broken ore and moves it to the ore pass or truck.
Manufacturer spec · 3 t payload · 1.3–1.5 m³ bucket

Haulage
15-tonne underground haul truck
Hauls ore and waste rock to the surface stockpile.
Manufacturer spec · 15 t payload · 7.5 m³ box
Models under review — not purchased or contracted. Images are illustrations of each equipment type.
Process flow
Drilling & blasting · loading · haulage
Crushing · grinding · gravity · flotation
Metal-specific recovery · concentrate handling
Refining & melting · quality assay · dispatch
Throughput planning
Planning scenarios that set the basis for plant design and ore supply.
Initial plan
Planning scenario45t/day
Reference throughput for trial and early operation.
Expansion review
Planning scenario180t/day
Four times the initial plan, reviewed against ore supply and operating results.
Design planning values — not installed capacity or production records.
Responsible development
Ground control, ventilation, haul routes, emergency response
Process water recycling, effluent treatment, water-quality monitoring
Tailings dewatering and storage, staged site rehabilitation
Haul hours, noise and dust control, open channel for residents